How Rack Denise goes onto the Unicell roof: feet through-bolted into the inside 1020 frame, every hole potted and bedded, a 1515 frame, six panels in two strings, one cable gland, then the fan, hatch, Starlink and a water test.

Where it stands, 2026-11-04Rack Denise and the six panels are ON the truck and charging. Jeff built the rack: 1515 frame, 1020 feet, through-bolted to a 1020 frame inside.Nothing else about it is recorded. Feet, stations, heights, panel size, gland and fan position are ASSUMED on the drawing. One trip up the ladder (step 1) fixes them.Still to do: inspect and re-seal every penetration, the cold-Voc check (step 3), VE.Smart networking (step 16), the fan and hatch clearance, the Starlink and antenna mounts, a water test and a torque record.Roof plan added 2026-11-04: a second, data gland forward of the Starlink; the 5G antenna (later) aft on the passenger rail; the passenger camera (later) on the rack over the awning.Decisions for Jeff: how does the Starlink cable get in today, and through what? Is the fan a MaxxFan, and does its lid clear the panel? Is the hatch an escape hatch? What is the panel model? Moto carrier still open.
Order list4 now, 12 after a check, 3 not yet

Prices as last seen; check before paying. "After a check" names the check in the step list.

Order now4

Order now
Butyl bedding tape

Under every foot pad and round every bolt shank: it never cures, so the joint can move on washboard and stay sealed.

Or: Home Depot, ~$7.98 listingHardware-store butyl, 50 ft, gray (Gibraltar 99415)
Order now
Tef-Gel anti-seize, 1 oz syringe

On every stainless thread into aluminium (T-nuts, extrusion, panel frames). Salt air plus stainless on aluminium corrodes and seizes without it.

Order now
Stainless cable ties, 11 in, 100-pack

PV and Starlink runs to the rack every 12 in. Plastic ties go brittle on a Baja roof in a season.

Order now$59.97
Husky 1/4 in drive torque wrench, 40 to 200 in-lb

For the first-drive re-check and every one after: the rack joints get a number, not a feel.

After a check12

After a check$14.45
Sikaflex 291, black, 10.1 oz

The build's sealant: the fillet round every foot, the gland base and the fan flange. Compatible with Raptor Liner (both polyurethane). Probably on the shelf already: count tubes first.

After a check
West System 105 resin, 205 hardener, 406 colloidal silica

Potting: only if the drill brings up foam or balsa core. Small sizes are plenty for 24 holes and a gland.

After a check
1/4-20 stainless button head cap screws

The roof bolts, foot pad to inside 1020. Length = pad + butyl + roof + 1/2 into the T-nut: buy once the roof is measured (step 2).

After a check
80/20 3675: 10-series 1/4-20 STAINLESS slide-in economy T-nut

Goes in the inside 1020's top slot under each roof bolt. Slide-in, so it loads from the member's end: plan them before the member goes up. Steel 3382 is the cheaper one if Jeff accepts zinc indoors.

After a check
80/20 3678: 15-series 5/16-18 stainless slide-in T-nut

For rack and panel joints that get redone outside: the rack lives in salt air, so stainless here, not zinc.

After a check$19.82
Stainless fender washers 1/4 x 1-1/4

Only if a bolt cannot reach a T-nut and goes through with a washer and nylock under the ceiling instead.

After a check
Stainless nylon-insert lock nuts 1/4-20

Same case as the washers. Nylocks, not split washers: split washers walk loose on washboard.

After a check
Scanstrut DS-MULTI-P-BLK multi cable seal

Two entries (2026-11-04): the aft one for power (4 PV wires, a spare), the forward one for data (Starlink, 4 antenna leads, the rack camera, a spare). Undrilled bung, drilled only for what goes through now. IP68. Buy only what is missing: keep a dry gland that is already up there.

1 or 2 · Scanstrut
Or: Scanstrut DS-H10Single-cable horizontal seal, cables 6 to 10 mm (DS-H10-BLK)
After a check$49.96
Step drill, 1/4 to 1-3/8

The gland hole and any overdrilled potting holes in the fiberglass skin. Cuts clean without grabbing.

After a check
Starlink Mini Roof Rack Mount (official)

Clamps bars 12 to 48 mm thick, up to 88 mm wide: a 1515 is 38 mm square, so it fits. Not for round bars. Only if the Mini has no fixed mount now.

After a check
10 AWG PV wire, red + black, 50 ft each, MC4 ends

Only if a string is rewired or the home run is too short to reach a new gland position.

1 pair · Signature Solar
After a check
U-POL Raptor 2K aerosol, black, RLB/AL

Touch-up where a foot was lifted or the coating was sanded for bonding, if the roof is Raptor-coated (not recorded).

1 · U-POL

Have it4

Have it
Rack Denise: the 1515 rack on 1020 feet

Designed and built by Jeff, on the truck since at least July 2026. This page records it; the order lines below are for inspecting, re-sealing, finishing or redoing it.

Have it
Six solar panels, about 1400 W, two series strings of three

On the rack and charging. Make, model and label values not recorded: step 1 reads them.

Have it
Two Victron SmartSolar MPPT 150/60

One per string. VE.Smart networking through the SmartShunt is planned, not on (step 16).

Have it
Starlink Mini

Mounted on the rack full time (Jeff, 2026-11-04). The drawing puts it aft on the driver rail: tape where it really is.

Not yet3

Not yet
Roof 5G MIMO antenna for the GL-X3000, 4 leads

LATER, only if cell keeps letting you down: Starlink is on full time and cellular is the backup (Jeff, 2026-11-04). 4x4 5G puck, low-loss LMR-200/240 leads, SMA ends, under about 15 ft to the router. Model not picked. Now: leave room for 4 leads in the data gland and a pull string down to the lounge box.

Not yet
Passenger camera on the rack

LATER, with the cameras. The awning case takes the passenger wall's top edge, so that face's camera hangs off the rack rail above it, on an aluminium angle bracket and T-nuts. Its Cat6 runs along the rail to the data gland. The other faces stay mid-face on the wall.

1 · Cameras
Not yet
Moto carrier: PAKMULE MotoMule (short tongue) + RambleSwing Pro

For the TW200 (278 lb wet). Not roof work: listed so it is not lost. Exceeds the 250 lb moto derating with a carrier on; ask RIGd whether the MotoMule raises it, or commission a custom swing.

Or: PAKMULEMotoMule on its own
Cut list9 parts

Inches. "Field-fit" means cut to the thing it meets, on the day.

partstockqtysize
Side rails80/20 15152167 1/2ASSUMED: re-cut only if redoing; measure the real ones in step 1
Crossbars80/20 1515678between the rails; ends square, anchor or bracket joints
Panel runners80/20 15152167 1/229 3/8 apart, under the panels' mounting holes
Foot pads80/20 1020126laid flat; two 9/32 holes 4 apart, drilled from the template
Foot uprights80/20 1020123 3/8ASSUMED height; sets panel clearance over the fan lid
Drilling template1/4 plywood16 x 2the pad's hole pattern; one template drills every foot
Antenna bracketaluminium angle 1/8 x 1 1/21about 4on the passenger rail, aft, by two 15-series T-nuts (later)
Camera bracketaluminium angle 1/8 x 1 1/21about 4on the passenger rail at mid-face, reaching out over the awning case (later)
PV home runs10 AWG PV wire2 pairsfield-fitto the gland with a drip loop; same length both strings is not required

Look and decidesteps 1 to 5

    1. Ladder, tape, phone. Rack Denise is already on: this step replaces the page's guesses with the real numbers.
    2. Count the feet. Tape each one's station from the outside face of the front wall, and its distance in from the driver wall.
    3. Tape the side rail spacing, each crossbar's station, the runners, and the height of the rail tops above the roof.
    4. Read one panel's label: make, model, watts, Voc, Vmp, Isc. Note how the panels hold to the rack (bolts through the frame, Z brackets, clamps).
    5. Find where the PV wires go through the roof and what seals them. Photograph every foot's sealant close up: cracked, lifted, or chalky is a re-seal.
    6. File the photos under capture zone ROOF (capture/zones.md lists it, nothing captured yet).
    Tope Every rack dimension on this page is ASSUMED from one sentence: 1515 rack, 1020 feet, bolted through into an inside 1020 frame. Send Jeff's numbers back and the drawing gets redrawn to them.
    1. Under each foot, find its bolt heads or nuts in the ceiling. Note which 1020 member each lands in, and any that missed the frame.
    2. Tape the hoop rib spacing (the page uses 16.8 on center, ASSUMED; dimensions.json says one tape settles it).
    3. Measure the roof thickness at one existing bolt: bolt length minus what you can see. The page uses 2, ASSUMED.
    4. Check where the over-bed ceiling panel will go. It is bonded on, and nothing serviceable may sit above it: any roof bolt over the bed must be checked and re-sealed BEFORE that panel goes up, or it is unreachable for good.
    5. Find the inside path from the gland to the MPPTs (electronics bay or garage). The drawing drops it aft, driver side, ASSUMED.
    Caution The ribs are galvanized steel hoops that run up the walls and over the roof. A new hole must miss them; a bolt through one is a new path for water into the steel.
    1. Three panels in series per controller. A SmartSolar 150/60 is destroyed above 150 V on its PV input, and panel Voc rises in the cold.
    2. Take the label Voc, times 3, times 1.12 for a cold morning (about 14 F). That number must stay under 150 with room to spare.
    3. A 12 V class panel (Voc about 22 to 24) gives about 80 V: fine. A 24 V class panel (Voc about 40 to 46) gives about 150 to 155 V cold: NOT fine.
    4. Run the label values through Victron's MPPT sizing calculator to be sure, using a Portland winter low, not a Baja one.
    Caution The panel model is not recorded anywhere. If the string is near 150 V cold, rewire each controller's three panels in parallel instead (Voc under 50 V), checking the three panels' Isc against the 150/60 datasheet limit, before winter.
    1. Roof fan: a MaxxFan Deluxe stands 5 closed and 9 5/16 open. The drawing has the panel underside at 7 1/2: under a panel, the lid cannot open fully. Fan model and position not recorded.
    2. Escape hatch: if it really is an escape hatch, it must open with a panel and a crossbar above it. The drawing has both over it.
    3. Starlink Mini: mounted on the rack full time (Jeff, 2026-11-04). Tape where it really sits and how its cable gets in today.
    4. 5G antenna: later, and only if needed (Starlink is primary, cellular the backup). Plan its place now: aft on the passenger rail, on a bracket, no new hole.
    5. Cameras: four at mid-face and one low at the rear (planning/cameras.md). The passenger one goes on the rack, because the awning case takes that wall's top edge.
    6. Count the cables: 4 PV, Starlink, 4 antenna leads, a camera and spares is more than one multi-cable seal takes. So two entries: power aft, data forward.
    Tip Every new thing on the roof should hang off the rack, not the roof. The rack is the only part already through-bolted and sealed.
    1. Butyl tape, Sikaflex 291 (count what is on the shelf first), Tef-Gel, stainless cable ties, the torque wrench (Order list).
    2. Bolts, T-nuts and washers only after step 2 gives the roof thickness and shows how the existing bolts are made.
    3. Epoxy only if a hole shows core (step 7). The gland only if the one up there is missing or full.

Feet and penetrationssteps 6 to 8

    1. Feet go over an inside 1020 member, never just through the skin. The drawing puts 6 stations, about 31 7/8 apart, ASSUMED.
    2. Make one drilling template: a 6 x 2 piece of 1/4 plywood with the pad's two holes, 4 apart.
    3. From INSIDE, drill a 1/8 pilot up through the open slot of the 1020 at each hole. The hole then lands over the slot, where the T-nut sits.
    4. Outside, line the template on the two pilots and check it is square to the box edge and clear of the fan and hatch.
    Tip Drilling the pilot from inside is what guarantees the bolt finds the T-nut. Measuring from the outside will not.
    1. Open each pilot to 9/32 for a 1/4-20 bolt, through the skin and the panel. Tape under the hole inside to catch the dust.
    2. Look at what comes out. If it is foam or balsa (the Unicell core type is not recorded): overdrill to 1/2 through the outer skin and core only.
    3. Rake the core back about 1/4 in round the hole with a bent nail in the drill. Tape the inside, fill with West 105/205 thickened with 406 to ketchup.
    4. Let it cure overnight. Re-drill 9/32 through the plug: the bolt now bears on epoxy, and water can never reach core.
    Caution Never leave raw core in a bolt hole. Water wicks along it, freezes in Portland, rots balsa or debonds foam, and the leak shows up feet away from the hole.
    1. Wipe the roof and the pad with isopropyl. A ring of butyl round each hole, and a layer under the whole pad.
    2. A twist of butyl under each bolt head too. Tef-Gel on the threads.
    3. Slide a stainless 3675 T-nut into the inside 1020 under each hole. Bolt the pad down: tighten until the butyl squeezes out all round and the pad seats, then stop.
    4. Torque about 50 in-lb, ASSUMED: no 80/20 figure was found for this joint, and more than that crushes a composite roof. Stop sooner if the pad bottoms.
    5. Next day trim the squeeze-out flush and run a Sikaflex 291 fillet round each pad, tooled to shed water. 291 is compatible with Raptor Liner.
    Caution Don't crank the roof bolts on the re-checks. The butyl stays soft; a bolt that turns easily is normal, a bolt that keeps turning has crushed the roof.

Racksteps 9 to 12

    1. Two 1515 rails, 167 1/2 long, on top of the uprights, about 4 1/2 above the roof (ASSUMED).
    2. 1020 to 1515 joints: 80/20 corner brackets or a 10-to-15 transition plate, stainless 15-series T-nuts, Tef-Gel on every thread.
    3. Sight each rail along its length, or pull a string: straight to 1/8. Shim at the upright, never by squeezing the butyl.
    1. 6 crossbars between the rails at the foot stations, 78 long.
    2. Anchor fasteners (end-tapped bars) or corner brackets, whichever the rack already uses.
    3. Measure both diagonals of the frame: equal within 1/8 means square. Then tighten everything.
    1. Two 1515 runners on top of the crossbars, along the box, under the panels' mounting holes.
    2. The drawing puts them at the panel's quarter points, 29 3/8 apart, ASSUMED. Measure the real panel's hole spacing and set them to it.
    3. Runner height sets panel clearance: the panel underside is 7 1/2 above the roof here, and the fan lid needs 9 5/16 to open.
    Tip If the fan lid has to open under a panel, this is where to buy the height: taller uprights or a second runner layer, before any panel goes on.
    1. The rack is rated walkable (exterior page). Prove it: stand at mid-span of each crossbar and each rail bay.
    2. Someone inside watches each foot's bolts and the ceiling round them. Nothing should move or creak.
    3. Look again at every Sikaflex fillet: a crack now means a foot is working.

Solarsteps 13 to 16

    1. Six panels in a row along the box, long side across, 3/4 gaps between them for cooling and drainage (ASSUMED layout from layout.html's elevation).
    2. Bolt each through its frame's mounting holes into 15-series stainless T-nuts in the runners: four bolts a panel, Tef-Gel on each.
    3. Keep the panel frames off the fan lid's swing and clear of the hatch, as decided in step 4.
    4. Number them 1 to 6 from the cab: string A is 1 to 3, string B is 4 to 6.
    Caution Never stand on a panel. Walk the rails and crossbars only.
    1. Each string: panel + to the next panel's minus, MC4 to MC4, three panels. Label both home-run ends A+ A- B+ B-.
    2. Run the home runs on top of the crossbars, under the panels, out of the sun and away from where feet go.
    3. Stainless ties every 12 in. No wire lying on the fiberglass, no wire across a sharp extrusion edge without a grommet or sleeve.
    4. A drip loop below the gland, so water runs off the bottom of the loop, not down the cable into the seal.
    1. Two glands. POWER, aft on the driver side over the garage: the 4 PV wires and a spare. DATA, just forward of the Starlink: its cable, room for 4 antenna leads, the rack camera, a spare. Positions ASSUMED.
    2. Keeping them apart keeps the PV wiring off the data cables, and neither seal is overfilled.
    3. Drill from Scanstrut's template with the step drill, then pot the hole exactly as step 7.
    4. Bed the base as Scanstrut's guide says, with Sikaflex 291 round the edge. Screws into potted holes too.
    5. Drill the undrilled bung for exactly the cables going through, not one hole more.
    6. Inside, run the wires to each MPPT through a PV disconnect or breaker (the electrical guide owns that end).
    Tip If a gland is already up there and dry, keep it as whichever entry it is closest to, and add only the other.
    1. PV disconnects open. Meter each home run at the MPPT end in sun: polarity right, Voc about 3 times the panel label.
    2. Battery side connected first, PV second. Close the disconnects. Each SmartSolar should show its own string's watts in VictronConnect.
    3. Then the open item: set up VE.Smart networking with the SmartShunt as the shared voltage reference, so both controllers run the same charge stage.
    Tope This one is overdue whatever else happens: the two MPPTs still each charge off their own terminal voltage (electrical page).

Roof gearsteps 17 to 18

    1. Open the roof fan lid all the way from inside. Under a panel it needs 9 5/16 clear (MaxxFan Deluxe spec, if that is the fan).
    2. If it hits, the fix is height (step 11) or moving one panel, not running the fan half open.
    3. Check the fan flange's sealant like a foot's: re-seal with Sikaflex 291 if it is cracked or lifted.
    4. Open the escape hatch from inside and see that it clears the rack and a person can get out. If it cannot, it is not an escape hatch any more.
    Caution An escape hatch that cannot open past the panels is worse than none: someone will count on it.
    1. Starlink Mini: already on the rack, on full time. It gets the clearest sky: nothing taller within a couple of feet, and clear of the open fan lid.
    2. Tall things go at the rack's ends and in the side strips, never on the panels' sun side: the Starlink, the antenna and the fan lid all cast shadow, and a shaded cell drags its string down.
    3. Its cable forward along the driver rail on stainless ties, a drip loop, into the data gland. Then down to the router in the lounge box.
    4. 5G antenna (later): aft on the passenger rail on an angle bracket and T-nuts, about 5 ft from the Starlink. Leads along the rail, across beside a crossbar, into the data gland. Now: a pull string and room in the seal.
    5. Passenger camera (later): on a bracket off the passenger rail at mid-face, looking out over the awning. Its Cat6 runs with the antenna leads.
    6. Everything hangs off the rack. No new hole in the roof except the data gland.
    Tip Pull strings and an undrilled spare position cost nothing now and save a roof job later.

Test and keepsteps 19 to 20

    1. A hose at garden pressure, 5 minutes on each foot, the gland, the fan and the hatch, one at a time.
    2. Someone inside with a flashlight, and a dry paper towel on each bolt head: a damp towel finds a leak before a drip does.
    3. Mark any leak, let it dry, re-bed that one joint, test it again.
    Caution Never pressure-wash at the seals, now or later. It drives water under butyl that a rainstorm never would.
    1. After 50 to 100 miles with some washboard: every rack joint and panel bolt to its number, then a paint-pen stripe across each head and its seat.
    2. The roof bolts: check, don't crank (step 8).
    3. Look at every fillet, the gland and the fan flange again.
    4. Then every 3 months, and after any long rough stretch: read the paint stripes, they show what moved. Check the Chili Boys front rack over the cab at the same time.
    Tip Write each re-check's date and anything that moved in the build log; a foot that keeps working is the first sign of a frame member or core problem.
Notes12
  • Source for the rack: Exterior & Rack and context.md: "All 1515 aluminum extrusion, bolted through the roof on 1020 feet, into a 1020 frame inside. Carries solar. Walkable." Built by Jeff; the 2026-07-12 log has the box and rack on. That sentence is the whole record.
  • ASSUMED on this page, measure before relying on it: box outside 171 1/2 x 87 1/2 (84 x 168 interior is spec, walls 1.75 and roof 2.0 are the truck model's placeholders); 6 foot stations at 6, 37 7/8, 69 13/16, 101 11/16, 133 5/8, 165 1/2 from the front wall; feet 3 in from each side; rail tops 6 and panel underside 7 1/2 above the roof; panels 26 13/16 x 58 11/16; rib spacing 16.8; fan at 89 and the hatch at 28 to 50; the gland aft on the driver side.
  • Solar: about 1400 W in 6 panels, two series strings of three, each to its own SmartSolar 150/60 (charge-sources working file; layout.html says the same). Panel make and model are not recorded anywhere in the repo; step 3's cold-Voc check depends on them.
  • The roof is drawn flat. The shell's hoop ribs curve over at the top (dimensions.json), so the outer few inches each side are radiused: feet that close to the edge sit on the curve. Check in step 1.
  • Over-bed ceiling panel: bonded up and sacrificial if the roof leaks above it (dimensions.json, decided 2026-08-10). Any roof bolt above it must be inspected and re-sealed before it goes up.
  • Roof fan: a 14 x 14 cutout is written on the joist; model not recorded. The MaxxFan Deluxe figures (5 closed, 9 5/16 open, 16 1/2 flange) are from its spec and only apply if that is the fan.
  • Front (cab) rack: fabricated by Chili Boys in Mexico, contact possibly Greg (unconfirmed). Separate from Rack Denise and not drawn here.
  • Motorcycle carrier (Yamaha TW200, 278 lb wet): RambleSwing Pro + MotoMule evaluated and over the 250 lb moto derating once a carrier is added; unresolved, see Exterior. Weight ratings unverified until RIGd confirms. Not roof work; the order list holds it so it is not lost.
  • Coating: Raptor Liner on the Unicell panels; Sikaflex 291 is confirmed compatible. Whether the roof itself is coated is not recorded.
  • Hardware rule from context.md: all stainless, Tef-Gel between stainless and aluminium, nylocks not split washers. Cameras (Cameras): mid-face on the 8020, except the passenger one, which hangs off the rack above the awning case (2026-11-04).
  • Roof plan, 2026-11-04: Starlink Mini on full time and primary; cellular is the backup, so the 5G antenna is planned (place, pull string, seal room) and bought only if needed. Two entries: power aft, data forward. Rules: everything hangs off the rack, tall things at the ends and in the side strips, the Starlink gets the clearest sky.
  • Roof bolt torque (about 50 in-lb) is a judgement for 1/4-20 stainless into a composite roof, not a published figure. If 80/20 or Unicell give one, use theirs.