TopeLeave about Dec 1
← Shower build

Shower this week

Measure, decide, order, buildShower and both doors

The next few days of the shower manual: the pan, what to tape, what to buy where, and what to build while the shipped parts are on their way.

1. The pan

The microcement is CimentART, and that decides it: their guide lists wedi as a substrate and warns against putting it straight onto sheet membranes. So the floor is the wedi Fundo base, bought as parts instead of the kit.

wedi Fundo Primo base, bought separatelyour pick
about $1,390 for the floor and all the board
CimentART: yes: CimentART lists wedi as a substrate
Base ships (call Portland Direct first). Boards, screws and sealant are on the shelf at Floor & Decor North Portland.
wedi Fundo kit, US2000001
about $1,525
CimentART: yes
The same parts in one box, plus about 45 sq ft of board you won't use.
Schluter Kerdi tray and drain
about $470
CimentART: no: CimentART won't go straight over a sheet membrane like Kerdi
Needs 1/2 to 1 cm of mortar over it before microcement: weight and thickness the 20 in room can't spare.
Plywood pan glassed with epoxy
about $250 to $300
CimentART: unknown: nothing from CimentART about epoxy
Lightest and most flex-tolerant, but no microcement on the floor; you'd paint it.
Stock RV pan
about $200
CimentART: no size fits
The largest stock size is 24 x 40; the room is about 52 x 20.

2. Measure

About an hour. Bolt heads first: that number changes what you buy at Crosscut. Photos with the tape in frame are as good as numbers.

3. Order and buy

Every item is stock off a shelf, custom from SendCutSend, printed on the P1S, or have it. Links and prices are on the manual's order list; custom part files on the parts page.

Order online now (ships)

Phone calls

Crosscut Hardwoods (walk in, after the bolt-head measurement)

Floor & Decor, North Portland (pick up)

Home Depot #4013 (aisles unknown, check the app)

Print on the P1S this week

Already have

SendCutSend, once the hardware is in hand (one batch order)

4. Build

Days 2 to 5 need only what you can carry home on day 2. The rest starts as the shipped parts arrive.

Day 1: measure and order

Day 2: the stock run and the D1 mockup

Day 3: cab wall

Day 4: the door frames and the cable box

Day 5: the curved ceiling

When the Scandvik arrives

When the base arrives

When the Husky track arrives