Systems / Power and light / Control box
Control box
The upper-cabinet box: the face, the boards, every cable in, beside the air fryer.
Divider, backplanes, entries, mount, the face, land every run.
Build
Every step in order. Scroll and the drawing follows: it builds up to the step you are on and lights what that step adds.
Plan step 1
1
Check the space
- Tape the box space, the 80/20 rails' heights and the air fryer in its bay: the Plan page's measurements.
Cabinet step 2
2
The divider
- 1/2 ply, full height and depth, 10 from the cabinet's left side.
- On the air fryer's side: a heat shield (foil-faced mineral or ceramic board) with a 1/4 air gap on spacers. Nothing of the box is screwed to the divider.
Caution Nothing electronic on the divider side of the box.
NeedsWaiting on 1 of 1
Divider: 1/2 ply with a heat shield on the air fryer's sideTBDInside steps 3 to 8
3
Backplanes
- Back plate: 1/4 ply, from just right of the QuinLEDs to the divider, full height, on four 4 in standoffs T-nutted to the two 80/20 rails: its face is 10 in back, in reach. Mount on it off the truck: fuse block, negative bus, Wago splits, signal strip.
- The 4 in behind it is the cable space: every run comes in there, loops, and comes round the plate's edge to its terminal.
- Left plate: 1/4 ply on the cabinet's left side, from 4 1/2 back to 10 back: the two QuinLEDs, one above the other.
Tip Everything on the back plate comes out as one board: four T-nuts.
NeedsWaiting on 7 of 7
QuinLED AorderedQuinLED Bready to orderFuse block, 6 ATC, with negative busready to orderNegative bus bar, 12 wayready to orderWago splits for the + slotsready to orderSignal terminal strip, 8 wayready to orderBackplanes: 1/4 ply on the left wall, and one on 4 in standoffs off the 80/20TBDCables step 4
4
Entries
- Top: a 1 1/2 grommet in the cabinet top at the back left for the ceiling runs.
- Low: a 2 in grommet low in the left side at the back for the chase runs, feeds, signal and climate cables.
- Every cable tied to the plate within 2 in of its grommet, labelled with its tag.
NeedsWaiting on 1 of 1
Grommets: 1 1/2 top, 2 in low leftready to orderInside steps 5 to 8
5
Mount and route
- Back plate on the rails, left plate on the wall.
- Ceiling runs down the back left corner to QuinLED B's terminals; chase runs up the back left corner to A's and B's.
The face steps 6 to 7
6
Cut and fill the face
- Cut the 10 x 13 panel to the face drawing: the Ekrano high and centred, the thermostat and EasyStart below, the eight rockers in a row, the USB-C pair at the bottom.
- Fit every device, hinge the panel on the cabinet's left side, two catches on the right.
7
Wire the face
- Every face device's cable in a loom to the hinge side, 12 in of loop, tied to the left plate: the face swings fully open with everything plugged in.
- Fuse block: Ekrano, thermostat, EasyStart, USB-C, the signal common. LIGHTS A and B rockers in the feeds; MAIN in the ceiling white's return (lighting page).
Inside step 8
8
Land every run
- The lighting page's channel table, run by run; each run's + on its fused slot (the + table).
Commission step 9
9
Test it
- Every test on the Test page.