Shower build
Order, measure, mock up, floor, dry structure, waterproof shell, finish, then the two doors last. The diagram follows the step you are on.
Ordering lives in 2 Plan and order: every part, where it comes from and where it stands. Each step below lists the parts it needs.
Cut list26 parts
Inches. "Field-fit" means cut to the thing it meets, on the day.
| part | stock | qty | size | |
|---|---|---|---|---|
| D1 hinge upright | poplar 1x2 | 1 | 72 | at corner C, 3/4 across the opening, 1 1/2 deep |
| D1 head | poplar 1x2 | 1 | ~20 3/4 | field-fit between the upright and the partition, under the 72 line |
| D1 apron | poplar 1x4 | 1 | ~20 3/4 | kitchen side, in front of the curb; no screw into the curb |
| D1 infill over the head | 1/2 plywood | 1 | ~20 3/4 x 4 1/4 | fixed; wedi and microcement over it |
| D1 leaf | 12 mm Baltic birch (have) | 1 | 18 x measured | CUT LAST. About 67 tall if nothing moves |
| D1 curb core | 3/4 white oak, two layers glued with epoxy | 1 | 20 3/4 x 3 1/4 x 1 1/2 | site-built (Jeff, 2026-10-21); top falls 1/8 to the shower; sealed, then 1/4 wedi on the top and shower face |
| Wardrobe-side fill | 1/2 ply | 1 | 1 3/4 x 39 | closes the strip of cutout behind the wardrobe face; glued to the cab ply edge and the wardrobe side |
| D2 infill | 1/2 ply | 1 | 5 11/16 x 39 | one piece from the doorway edge to the hole's edge, cut to fit last; flush on the shower side, 1/8 back on the cab side (the cab ply is 5/8) |
| D2 leaf | 12 mm Baltic birch (the D1 sheet offcut) | 1 | 20 11/16 x measured | CUT LAST. About 36 with the top rail |
| D2 top rail | poplar or oak 5/4, 7/8 to 1 thick | 1 | 20 11/16 x 1 1/2 | glued and screwed on the leaf top: the hanger zone is 20 mm or more |
| Track | Husky aluminium, 6 ft | 1 | 41 1/2 | trim only after the bench mockup |
| Upper band skin | 1/4 Baltic birch (have) | 1 | 52 1/4 x 7 1/4 | top edge scribed to the ceiling curve |
| Upper band ribs | 3/4 plywood, scribed | 4 | ~7 1/4 tall | about 3/8 deep, so the skin lands flush with the factory plywood |
| Driver skin | 6 mm okoume | 1 | 21 1/4 x 76 1/4 | top edge follows the ceiling curve at the cab end |
| Lower wall ribs | 3/4 plywood | 4 | 3 3/8 x 47 1/8 (the cab corner one 43 7/8) | on the 80/20's 22 and 45 bars; a notch at the back foot for the cables; the cab corner one stands on the cable box top |
| Shelf plate | 3/4 plywood | 1 | 3 3/8 x 18 1/4 | across the rib tops, its top 47 5/8 up: the shelf's wedi sits on it, a hair of fall toward the room |
| Corner cleats | poplar 2x2 ripped to 1 x 1 1/2 | 2 | 20 7/8 and 19 7/8 | above the shelf, in the 80/20's plane: one on the cab ply, one by the partition under the 68 bar |
| Batten above the shelf | poplar 2x2 ripped to 1 x 1 1/2 | 1 | 11 3/4 | 80/20 upright to the partition cleat, 58 up |
| Fixture blocks | 3/4 ply (mixer), 1 in poplar (hook) | 2 | 8 1/2 x 8 (mixer, between its ribs) + a 3 x 3 pad (hook) | the mixer's block waits for the mixer: its depth comes from the valve; the hook's pad in the 80/20's plane under the 68 bar |
| Ceiling profile ribs | 3/4 plywood | 3 | 21 1/4 long | one each side and one in the middle, cut from templates of the real shell, not the drawing; the middle one glued to the shell |
| Ceiling battens | clear 1x2 | 5 | ~50 3/4 | across the curve, 6 in apart at most |
| Ceiling skins | 3 mm okoume | 2 | ~52 1/4 x 24 | laminated over the ribs; the second staggers the first's joints |
| Cable box blocks | 2x4 ripped to 2 | 7 | 2 x 1 1/2 x 2 3/4 tall | every 6 in across the passthrough, none over the cables |
| Cable box top | 1/2 plywood | 2 | 20 1/16 x 2 3/4 and 30 5/16 x 2 | they meet over the block at the doorway line; the driver end runs on under the cab corner rib |
| Cable box back | 1/2 plywood | 1 | 20 1/16 x 2 3/4 | the box's cab side, only where the passthrough is |
| Fundo base | wedi Primo 36 x 72 (kit) | 1 | ~48 7/8 x 17 7/8 | trim asymmetrically: drain 32 1/4 from the wardrobe end; remake the 1/2 x 1/2 edge channel |
The wedi kit, piece by piece5 boards, 1 base, 1 curb
Kit US2000001: the 36 x 72 centre-drain base with its drain and stainless cover, six 3 x 5 boards of 1/2 in wedi, one 60 in Lean curb, a box of 100 screws and washers, and Joint Sealant. Sizes are the model's, to be field-fit. Tall walls get one level seam 60 up from the base, sealed with Joint Sealant like every other seam.
every wall, the ceiling and the cable box, all 1/2 (the kit has no 1/4) offcut
| piece | board | size | ||
|---|---|---|---|---|
| A | Cab wall beside D2, lower | 1 | 31 11/16 x 60 | 1/2 plan |
| B | Driver wall above the shelf, cab half (scribe the curve) | 1 | 10 5/8 x 28 | 1/2 plan |
| C | Driver wall above the shelf, kitchen half | 1 | 10 5/8 x 28 | 1/2 plan |
| D | Cable box face (D2's curb) | 1 | 48 7/8 x 3 1/2 | 1/2 plan |
| E | Partition, lower | 2 | 31 x 60 | 1/2 plan |
| F | Cab wall beside D2, top | 2 | 31 11/16 x 6 7/16 | 1/2 plan |
| G | Cable box top | 2 | 48 7/8 x 2 1/2 | 1/2 plan |
| H | Over the D1 head | 2 | 20 3/4 x 4 1/4 | 1/2 plan |
| I | Shelf top | 2 | 20 3/16 x 3 3/8 | 1/2 plan |
| J | Wardrobe wall, lower | 3 | 17 x 60 | 1/2 plan |
| K | Ceiling, flat and curve (relief-cut the curve) | 3 | 51 1/4 x 23 1/2 | 1/2 plan |
| L | Driver wall, below the shelf | 4 | 20 3/16 x 45 13/16 | 1/2 plan |
| M | Cab wall over D2 | 4 | 20 1/16 x 30 15/16 | 1/2 plan |
| N | Wardrobe wall, top (scribe the curve) | 4 | 17 x 13 13/16 | 1/2 plan |
| O | Partition, top | 5 | 31 x 14 3/16 | 1/2 plan |
- Boards. The kit has 100 sq ft, all 1/2. Every wall gets it (Jeff, 2026-10-12: the wardrobe and partition were drawn in 1/4, which the kit doesn't have): 66 of 100 sq ft on all six boards, so 34 sq ft (34 percent) is offcut. The 1/2 on the wardrobe and partition costs about 1/4 in on each.
- Base. The shower floor takes 6.1 of the base's 18 sq ft; the rest (66 percent) is trimmed off. That is the cost of a centre-drain base in a room this shape: the drain is 32 1/4 from the wardrobe end, so the long way needs a 72. Keep the offcuts: they are sloped wedi foam, good for a niche floor or test pieces for the microcement.
- Curb. D1 takes 20 3/4 of the 60 in curb (D2's curb is the cable box), 39 1/4 left over.
- Screws. Roughly one screw and washer per sq ft at the wedi spacing: about 66. The kit's 100 covers it.
- Joint Sealant. Count the tubes when it arrives. At about 1.2 oz per sq ft of board it wants about 8 tubes, plus the base and curb joints. Buy one spare if the box is short.
- Ceiling. One piece, 51 1/4 x 23 1/2 laid flat. The cab end bends on about an 10 5/16 radius, so it needs relief cuts on the back at the spacing wedi gives, each one filled and sealed.
- Not in the kit: the setting thinset for the base and curbs (modified, ANSI A118.4 or A118.15, on the bag).
The ceiling curve, layer by layer
Section through the shower from the cab wall (left) to the partition (right), to scale. The rib's bottom edge is the line everything else follows: flat at 76 1/4 for 12 in from the partition, then one curve down to 70 1/2 at the cab wall (about a 10 5/16 in radius). Under it: two 1/8 skins, 1/2 wedi, microcement, 9/16 in all, so the finished ceiling is 75 11/16 flat and 69 15/16 at the cab wall.
- Trace, both sides. Cardboard flat against the driver wall up at the ceiling: trace the shell and the 8020 from the partition to the cab wall. The same against the wardrobe side; they may differ. On each, draw the ceiling line: level at 76 1/4 for 12 in, then the curve to 70 1/2 at the cab wall. Keep 1 1/2 in of wood above that line over the curve.
- Cut three ribs from 3/4 ply, each 21 1/4 long: one from each template, and a third for the middle (use the driver-side template). Only the bottom edge matters: cut it a hair proud, then sand it to the line with a long sanding block so it is fair, no flats or bumps.
- Nothing on the curve to fix to (Jeff, 2026-10-12: the curve is bare fiberglass, no ribs). So each new rib is held at its two ends and only glued in between. Its kitchen end is the 12 under the flat ceiling: screw it up into the 8020 there. Its cab end sits on the top of the cab wall's upper band (build the band first) and screws into its ribs. In between, glue the rib's top edge to the fiberglass with PL Premium so it can't rattle. The curve is only 9 1/4 across, so a 3/4 ply rib held at both ends is plenty. No screw goes into the shell.
- Where they go: one against each side wall (screwed to it as well where there's wood or 80/20 to bite), one in the middle, 26 1/8 from the wardrobe face. Lay a long level across all three in four places: the bottom edges at the same height, or the ceiling twists.
- Battens: 5 poplar 1x2, about 50 3/4 long, across all three ribs over the curve, their bottom faces exactly on the curve (plane the edge to it). Glue and screw through the side ribs into their ends, and up through each batten into the middle rib's edge. They go on the ribs, never on the fiberglass. The flat part needs none: the skins screw straight up into the 8020.
batten out from the cab ply its bottom face, up from the floor 1 9/16 71 1/2 2 2 73 5/16 3 3 13/16 74 11/16 4 5 7/8 75 11/16 5 8 1/8 76 3/16 - Check the frame with a strip of 1/8 ply bent across it: it should touch every rib and batten with no gap and no bump. Run the light leads now (they are inside after the next step).
- Skin 1: one 1/8 sheet about 52 1/4 x 24 1/2, the whole ceiling. Test-bend a scrap first; if it fights, turn the sheet 90 degrees (ply bends far easier one way). Glue every rib and batten, start at the partition and roll it into the curve toward the cab, screwing as you go: into the 8020 over the flat, into the battens and ribs over the curve.
- Skin 2: a second 1/8 sheet glued all over the first, its joints a few inches off skin 1's. Screw it while the glue sets; the two together make the ceiling stiff, give the wedi a smooth bed to glue to, and take its screws anywhere.
- The wedi: one board for the whole ceiling, kerfed to bend (Jeff, 2026-10-12). Cut it 51 1/4 x 23 1/2 from the kit's 1/2. On its back, mark the flat part: the first 12 from the partition end stays uncut. From there to the cab end, saw kerfs straight across the board, 1/2 apart and 1/8 deep (half the board, the usual rule for scoring it): 23 of them. Table saw with the blade set to 1/8, or a track saw.
- Test first. Kerf a 6 x 12 offcut the same way and bend it over your cardboard template, face down, the way it goes up. The face is on the inside of the bend, so it gets squeezed: look at it under a raking light. No cracks or crazing: go ahead. If the face crazes, use the fallback, 6 strips about 1 15/16 wide laid like staves, every joint sealed and taped.
- Why the kerfs beat strips: the face and the front half of the foam stay whole across the curve, so there are no seams up there to trust to sealant; the strips would give 5 joints over your head. The foam is what keeps water out; the kerfs only cut the back half, which faces the skins.
- Hang it: wedi 610 or thinset on the skins and the board's back (it fills the kerfs as they open), push it up flat end first, roll it into the curve. Screw and washer it every 6 in along each batten and rib (wedi's ceiling spacing) and into the 8020 over the flat; keep screws off the kerf lines.
- Where it meets the cab wall, the ceiling board butts the cab wall's wedi (which comes up over the upper band) in an inside corner: sealant and tape it like every wall corner.
- Microcement over the lot with the mesh in the first coat; feather the curve, don't fill it.
- Ask wedi to confirm the kerf spacing for a curve this tight (about 10 5/16 in radius, face on the inside) before you cut the real board: it is their warranty.
Order and checksteps 1 to 5
- The wedi kit is ordered (Home Depot, pickup at SE 82nd Ave, due Oct 21): base, drain and cover, six 1/2 in boards, the Lean curb, screws, Joint Sealant. Buy the setting thinset at pickup.
- Order the VETUS FAN12 and its SCIROCCO cowl (Fisheries Supply, Seattle: order online), the TACO piano hinge (Fisheries Supply or West Marine).
- Call Woodward's about the Husky pack: it has to fit a 3/4 in leaf with a 7/8 in hardwood top rail, and the shortest track is 6 ft.
- Home Depot: poplar 1x2 (two 8 ft), 1x3 and 1x4 (2 ft each) for both door frames. Crosscut: 6 mm okoume for the driver wall. The upper band skin is 1/4 Baltic birch you have.
Tip The frames come first: they set both door openings, and the door leaves and the wall pieces are measured off them.- Cab wall bolt heads: the tallest is 1/4 (taped 2026-10-06), and the upper band's ribs keep its 1/4 Baltic birch skin clear of every head.
- The shell above the shelf and the ceiling curve: trace both onto cardboard full size. The ribs are cut from the tracing, not the drawing.
- Fan zone: its centre from corner A and down from the ceiling, the wall thickness there, and the gap to the cargo box outside (3 1/2 in August).
- Mark the drain on the vinyl: 20 in from the driver 80/20, 12 1/2 in from the cab plywood.
Caution Every height you measured off the vinyl is 1/8 low once the vinyl is out. Add 1/8.- When the Husky parts arrive: screw the uncut track to a scrap board, hang a 19 x 3/4 scrap leaf with a hardwood top rail.
- Slide it 20 11/16 in. Closed, it laps the opening 1/2 each side; parked, it stops 1/4 before the cable box.
- Set the two clip stops and the BG1 guide there. Only then mark the track's cut.
Tip Plan or 3D tab, Doors: Open D2 shows it sliding to parked.- Stand in the room: the mixer on the lower wall (the page puts it 40 up, over the drain), the shelf top about 48 up, the hand shower's hook above it (about 66). No rail: the head hangs on a removable hook.
- Mark the mixer's holes and the space its supply fittings need behind the lower wall, and the hook's spot.
- Those marks set the mixer's backing block and the hook's pad.
- When the kit arrives, before any glue: lay the Fundo base on the vinyl with its drain over your mark.
- Mark the trim lines: it comes down to about 48 7/8 x 17 7/8, more off the driver end than the wardrobe end (the lower driver wall stands 4 in out).
- Keep 2 in from the drain opening to any cut, and remake the 1/2 x 1/2 channel along each cut edge with 1/4 in of base left under it.
- Mark both curbs: D1 in the partition opening (about 20 3/4), D2 in the cab passthrough (about 20 1/16). Both from the one 60 in curb.
- Trace the base and curb footprints onto the vinyl.
Dry structuresteps 6 to 26
- First, before any framing: every height in the plan is from the bare subfloor, and the framing stands on it. Left in, the vinyl puts everything 1/8 high.
- Score the vinyl along the wardrobe face, the 80/20 face, the cab plywood and the partition's shower face, and across the D1 doorway in line with the partition's kitchen face. Lift it inside those lines only: it stays under the wardrobe, the partition and the kitchen. Scrape the glue off.
- The base, the curbs, the cable box and the lower wall cover all of it later; the D1 apron hides the cut edge from the kitchen. The drain hole waits for the base dry-lay (step 27).
- Mark the lines everything is measured from: the wardrobe face (every "from the wardrobe" number starts there), the D2 doorway line at 20 1/16, the lower wall's rib faces 3 3/8 out from the 80/20, and the shelf plate's top at 47 5/8 on the cab plywood and the partition.
Tip The framing order: D2 frame, the lower wall's ribs, the cable box, the corner rib and the shelf plate, above the shelf, the upper cab band, the ceiling ribs, the laundry panel. Each is measured off the one before.- The cab passthrough starts 1 3/4 behind the wardrobe face, so from the cab you'd see the wardrobe's end. This strip closes that.
- No cleat (Jeff, 2026-10-21): the strip is glued to the hole's wardrobe edge and to the wardrobe's side, and held by the cab wall's finish.
- Cut 1/2 ply (an offcut: it stays dry) to 1 3/4 x 39, the hole's full height. Set it in the hole against the wardrobe line, its shower face flush with the cab plywood (the cab ply is 5/8, so the 3/4 strip stands 1/8 proud on the cab side: ease that edge), and glue and screw it to the cleat, and to the wardrobe's side where it touches.
- Finish the face you see from the cab to match the cab wall.
NeedsReady: everything is in handD2 fill strip behind the wardrobe, 1/2 plyhave it- No separate post (Jeff, 2026-10-21): the infill's edge is the doorway's driver side. Mark it plumb on the floor and the cab ply, 20 1/16 from the bare wardrobe face: 19 3/4 clear from the wedi.
- Measure wardrobe face to the line at the bottom, the middle and the top: 20 1/16 at all three.
- One cleat only, at the floor on the shower side (inside the cab box). The rest is glue, temporary battens on the cab side, and the cab wall's wedi over both seams.
- 1/2 ply, cut to fit from the line to the hole's edge (about 5 11/16) x 39. PU glue on its edges, its doorway edge on the line, its foot screwed to the floor cleat, its shower face flush with the cab plywood (1/8 back on the cab side). Screw two scrap battens across each joint from the cab side, with a 1/8 shim on the infill, until the glue and the wedi cure.
- Sand and round its doorway edge and seal it: the wedi stops at it and the microcement wraps it, like the hole's top. The door laps it when shut; the closed latch's keeper and the BG1 guide screw into its face.
- Finish the cab-side face to match.
- No head (Jeff, 2026-10-12): the opening is the hole's full height, 39, so 35 1/2 clear above the cable box. The door laps the hole's top edge by 3/4.
- The hole's top edge is the cab plywood's cut edge: sand it straight and round it slightly, seal it, and let the cab wall's wedi stop flush with it. The microcement wraps the edge with its mesh, so the doorway's top is one clean line.
- The track hangs above the hole on a bracket bolted right through the cab plywood: 1/4-20 stainless, fender washers and nylocks (or cap nuts) on the cab side. The track isn't ordered yet, so don't drill: keep the band from 39 to about 44 1/8 up clear of screws and wedi seams.
NeedsWaiting on 1 of 1D2 track bracket: a bent stainless angle the track hangs fromTBD- First the curb (Jeff, 2026-10-12): the wedi Lean curb cut to 20 3/4, the whole opening, wardrobe to the partition's edge, its kitchen face flush with the partition's kitchen face. Bed it level on the subfloor in wedi sealant. The frame stands on it, so one unbroken curb keeps the water in.
- The upright: poplar 2x2 ripped to 1 1/4 x 1 1/2, 67 1/4 long, curb top to the head. It stands on the curb at the wardrobe end, its kitchen face flush with the curb's and the partition's.
- Plumb it both ways. Glue it and screw it to the wardrobe's side panel: six #8 x 1 1/4 through its opening face, about every 12 in, countersunk. Its foot sits on the curb in a bead of sealant: no screws into the curb (it is foam).
- The door's weight hangs on this piece, through those six screws.
- The hinge's frame leaf goes on its opening face later, in the corner by the shower side: keep that strip clear of screws (they go in the kitchen half).
- The same 2x2 stock ripped to 1 1/4 x 1 1/2, 67 1/4 long, standing on the curb against the partition's edge. Before it goes in, cut the notch along its shower-side inner corner on the table saw: 5/8 across and 1 deep, two passes. The door's lip drops into it.
- Stand it against the partition plywood's edge, flush with the upright both sides, notch facing the door and the shower. Plumb it. Glue it and screw it into the partition's edge: six #8 x 1 1/4 through its opening face in the kitchen half, every 12 in.
- That leaves 5/8 of full-depth poplar behind the notch: the latch's keeper screws into that, never into plywood edge.
- The same stock, 1 1/4 tall, 20 3/4 long, with the same 5/8 x 1 notch along its bottom shower-side corner, meeting the jamb's notch in the corner.
- It sits ON TOP of the upright and the jamb, 20 3/4 long, the full width, top at 72, level. Its notch runs across the opening and meets the jamb's in the corner. Glue it and drive two screws down through its top into each post's end; the infill covers them.
- The opening is now 18 1/4 wide and 67 1/4 tall above the curb, and the kitchen face is one flat plane.
- 1/2 ply, about 20 3/4 x 4 1/4: it closes the gap from the head up to the ceiling.
- Scribe its top to the ceiling. Screw it to the head, the upright and up into the ceiling frame.
- wedi and microcement go over it later, like the walls.
- The poplar 1x4 apron goes on the kitchen side much later, after the curb (step 29).
NeedsReady: everything is in handD1 infill above the head, 1/2 plyhave it- With both frames in, measure each opening at three heights and three widths. Use the smallest.
- D1: cut the 12 mm Baltic birch to 18 wide and about 67 1/4 tall, 1/4 over. Trim it to a 1/8 gap all round once the frame is finished.
- D1's lip, the catch: a 1/8 x 1 poplar strip glued and screwed (#6 x 3/8 every 8 in) along the strike edge and the top of the shower face, half on the door and 1/2 past its edge. Two cup magnets set flush in the overhang, near the top and the bottom.
- D2: cut the 12 mm Baltic birch (from the D1 sheet) to 20 11/16 wide and about 36 1/2 tall with the 5/4 top rail on, 1/2 over. It gets its final trim once the Husky hangers are in and it hangs.
- Dry-fit each one: D1 in its opening against the upright, D2 held over the passthrough. Mark the hinge edge, the latch edge and the top on each.
- D1's air slots, while it's on the bench: five through-slots 5/16 x 11, 3/4 apart, centred across the door, the lowest 7 in up. A router with a 5/16 straight bit against a clamped straightedge, a pass from each face. Round the ends, then epoxy every slot's edges.
- Seal every face and edge, then set them aside. They go back on last, after the finish.
Tip Cut them now, a little big, so the walls can be planned round real doors. Trimming 1/4 off later is easy; adding it back is not.NeedsWaiting on 4 of 5D1 air slots, routed through the doorready to orderD1 leaf, 12 mm Baltic birchhave itD1 catch lip, 1 x 1/8 black anodized aluminum bar on the door's shower faceready to orderD1 corner magnets: cup magnets and steel strikesready to orderD2 leaf, 12 mm Baltic birch (the D1 sheet offcut), hardwood top railready to order- No overlay: the wedi goes straight onto the factory plywood, which is the solid backing its screws need.
- Hold a long straightedge across the wall in a few places. Apart from the bolt heads it should be flat; mark anything proud and plane or sand it.
- Leave the bolt heads alone. Note roughly where each one is, so you can keep the wedi's seams and screws a few inches off them later.
- The pockets for them get cut in the back of the wedi boards at step 30.
NeedsWaiting on 1 of 1Stainless #8 x 1 1/4 flat-head screwsready to order- Above the shelf the shell steps back 5/8. Scribe four plywood ribs from your tracing to bridge it, 63 1/4 up to the ceiling.
- Skin them with 1/4 Baltic birch so the face is flush with the factory plywood below. One flat wall, only its top edge follows the curve.
- Leave room between two ribs for the fan's blocking ring (step 22).
- The wall below the shelf stands 4 out from the 80/20 when finished: 4 ribs 3 3/8 deep, a plate on top, then wedi and microcement. The cables and PEX run behind it along the floor; the mixer sits in it.
- Rib positions, from the cab plywood: -1/8 to 5/8; 6 5/8 to 7 3/8; 15 7/8 to 16 5/8; 20 1/8 to 20 7/8. The second sits on the 80/20 upright; the third is 8 1/2 past it, the mixer's space. The first (the cab corner) goes in after the cable box.
- Cut three at 3 3/8 x 47 1/8, grain running up. Notch each back foot to clear the bundle by 1/4 (drawn 0 deep x 0 high), keeping 3/4 of rib in front.
- Each stands on the subfloor, back edge on the bars, front edge on the line 3 3/8 out from the 80/20 face. Plumb it, then a steel corner brace at the 22 and 45 bars: screwed to the rib, bolted into the bar's slot with a drop-in T-nut. The one on the upright gets a brace into the upright too. The partition rib is glued to the partition as well, no screws through to the kitchen. A brace at each foot into the subfloor.
- A straightedge across the rib faces: one flat plane, 3 3/8 out everywhere. Plane or shim now; the wedi goes straight onto these faces.
- The mixer (Jeff, 2026-10-12: a real mixing valve) goes between the second and third ribs about 40 up. Its block waits for the valve: the valve's rough-in depth sets how far back it sits. Sit on the toilet spot and check your head clears the shelf corner.
NeedsWaiting on 4 of 6Driver-side box over the PEX: two 1/2 ply walls and a 1/2 ply top, the lower wall stands on ithave itDriver wall above the shelf: two corner cleats and a batten, poplar 2x2 ripped to 1 x 1 1/2ready to orderLower driver wall: 1/2 ply ribs and shelf plate, 4 in outhave itFixture blocks, 3/4 okoumeready to orderStainless #8 x 1 1/4 flat-head screwsready to orderMixer drilling templateTBD- One fixed box from the wardrobe face to the lower driver wall, 3 1/2 high and 2 1/2 out from the cab plywood when it's done: the cab doorway's curb and the cables' cover. The frame is 3 1/4 x 2; the kit's 1/2 wedi on its face and top makes up the rest.
- Measure the bundle where it runs along the cab plywood: how far it stands off it, and how high. The plan assumes it fits in 2 x 2 3/4. If not, stop: the box comes out further and D2 moves with it.
- Blocks: rip a 2x4 to 2 wide and cut 7 blocks 2 3/4 tall. Their left edges, from the wardrobe face: 0, 6, 12, 19 5/16, 24, 30, 35. The one at 19 5/16 straddles the doorway line so both tops land on it. None past 36 1/2: the cables are there.
- Glue each block down and drive two screws into the subfloor (check its thickness first, so nothing comes out underneath). Where there's cab plywood behind, screw into that too.
- Back: where the passthrough is, nothing is behind the blocks. 3/4 ply, 20 1/16 x 2 3/4, in the hole flush with the cab plywood from the wardrobe line to the doorway line, glued and screwed to the blocks.
- String or a straightedge along the block tops: all at 2 3/4. D2 hangs 1/4 above the finished top, so a wavy top shows.
- Top A, 1/2 ply 20 1/16 x 2 3/4: wardrobe line to the doorway line, over the back's top edge. Top B, 30 5/16 x 2: the doorway line to 50 3/8, 1 1/2 past the rib line into the corner. Glue and screw both into the blocks. Over the cables top B spans on its own until the corner rib stands on its end (step 182).
- Later, with the kit: 1/2 wedi on the face (sealant to the blocks and the top's edge, wedi screws and washers into the blocks) and on the top, lapping the face's wedi, running through the doorway to the cab face. The base then butts the face.
- The cab corner rib, 3 3/8 x 43 7/8: it stands on the end of the cable box's top B, against the cab plywood. Glue and screw it to the cab plywood every 8 in, its front edge in the plane of the other ribs, and drive two screws up through the box top into its foot. It carries the box's end over the cables.
- The plate: 3/4 ply, 3 3/8 x 20 3/4, across all four rib tops, its top 47 5/8 up. Shim its back edge 1/16 higher than the front so the shelf sheds into the shower. Glue and screw it down into every rib. The finished shelf is 48.
- Insulation into the bays after the PEX is pressure-tested, never before.
- No skin above the shelf: the wedi goes straight onto the 80/20 (the 68 bar and the upright at 7). These give it its two edges and a line across the middle, so no part of the board spans more than about 12 in.
- Rip a poplar 2x2 to 1 x 1 1/2. The 1 in is the 80/20's depth, so every piece lands flush with its face, the 1 1/2 face toward the shower.
- Cab cleat, 20 7/8: upright against the cab plywood in the 80/20's plane, plate to just over the 68 bar. Glue and screw it to the cab plywood every 8 in.
- Partition cleat, 19 7/8: upright against the partition, plate to the underside of the 68 bar. Glue it to the partition, two screws up through the plate into its foot, a corner brace and T-nut into the 68 bar at its top.
- Batten, 11 3/4: from the 80/20 upright to the partition cleat, centred 58 up. A corner brace and T-nut at the upright; glue and two pocket screws into the cleat.
- Hook pad, 3 x 3 x 1: centred 12 1/2 from the cab plywood, right under the 68 bar, a brace and T-nut into the bar. Move it if the dry-fit put the hook elsewhere.
- A straightedge across the 80/20 and every piece: one plane. Later, where the wedi lands on aluminium it gets sealant on the metal and stainless self-drilling screws through wedi washers; into the poplar, wedi's own screws.
- Tape the fan's paper template inside (5 1/8 face) and the cowl's outside (5 13/16 x 4 15/16). Check: clear of the marker light, the plywood edges, any structure, and at least 1 in from the Pelican box behind it (3 1/2 gap measured).
- Drill a small pilot from inside and look at where it comes out before the 3 in hole saw goes through the shell.
- A 3/4 plywood blocking ring between the ribs around the hole, glued and screwed.
- A second blocking ring 10 in toward the driver side, no hole: a ready spot if a second fan is ever wanted, so its hole later goes through solid backing.
- The 3 in sleeve through it all, with a slight fall to the outside so water runs out, not in. Cut it flush with the finished wall later.
Caution It is the only hole through the shell in the shower. Measure twice from inside and outside before cutting.- What you're building: a new ceiling surface that is flat at 76 1/4 for the first 12 in from the partition, then curves smoothly down to 70 1/2 where it meets the cab wall. It follows the shape of the box's roof, so you keep the headroom.
- Make two templates. Hold a piece of cardboard flat against the driver wall, up at the ceiling, and trace the shape of what's above (the shell and the 8020) from the partition to the cab wall. Do the same against the wardrobe side. They may not match.
- On each template, draw the line you want the ceiling to be: level at 76 1/4 for 12 in from the partition, then a smooth curve down to 70 1/2 at the cab wall, close to a 10 5/16 in radius. Keep at least 1 1/2 in of space between that line and the traced shell over the curve.
- Cut three ribs from 3/4 plywood with the templates (the third, for the middle, off the driver-side one), each about 21 1/4 long: the top edge follows the shell, the bottom edge is your ceiling line. The bottom edge is the one that matters; sand it smooth and fair.
Tip Lift ceiling in the 3D tab shows the room under it.NeedsWaiting on 1 of 1Ceiling profile ribs and battensTBD- The curve is bare fiberglass, no ribs (Jeff): each new rib is held at its ends. Its kitchen end, the flat 12 in, screws up into the 8020; its cab end sits on the upper cab band (step 17, first) and screws into it; its top edge is glued to the fiberglass with PL Premium in between. One against each side wall, one in the middle. No screws into the shell.
- Lay a level across all three at a few places: the bottom edges must be at the same height, or the ceiling twists.
- Five clear 1x2 battens, about 50 3/4 long, across all three ribs over the curved part, never onto the fiberglass, no more than 6 in apart, their bottom faces exactly on the curve. Glue and screw through the ribs into their ends, and up into the structure where you can reach it.
- Over the flat part the skins fix straight up to the 8020, so it needs no battens. Check the whole frame with a strip of 3 mm ply bent across it: it should touch everywhere with no bumps.
- Now run the two light leads (step 33) to their spots in the flat part, 6 in from the partition and a third of the way in from each side, and on over the laundry cubby to the kitchen. Label both ends. After the skins go on you can't get to them.
- Test-bend a scrap of the 3 mm okoume over the curve first. If it fights, turn the sheet the other way: plywood bends much more easily one way than the other.
- Skin 1: one piece of 3 mm okoume about 52 x 24, the whole ceiling. Glue on every rib and batten, then staple or screw it: up into the 8020 over the flat part, into the battens and ribs over the curve. Work from the flat end toward the cab so it rolls into the curve.
- Skin 2: a second 3 mm sheet glued all over the first, its joints a few inches off the first's. Clamp or screw it while the glue sets; it's what makes the ceiling stiff.
- Leave the light leads poking through a small hole at each light spot. The light holes are cut full size at the wedi stage.
NeedsWaiting on 1 of 1Ceiling skins, 1/8 Baltic birch or 3 mm okoume, x2ready to order- The strip between the wardrobe top and the ceiling, 20 3/8 long, is open to the shower. A 1/2 ply panel on the wardrobe's shower-side edge closes it, and the wardrobe wall's wedi runs up over it to the ceiling.
- Its top is the ceiling line, so cut it from the same wardrobe-side cardboard template as the ceiling rib (step 23). The heights here are the plan's line, to check the template against.
- 1/2 ply, 20 3/8 long x 4 1/8 tall: flat for the first 12 from the kitchen end, then curving down to the wardrobe top near the cab end. Jigsaw a hair proud and sand to the line.
- Stand it on the wardrobe top, its shower face flush with the wardrobe's shower face. Glue and screw it down into the wardrobe side (check the side's thickness, so no screw comes out inside), and into the ceiling rib once that's in.
- The flap, the liner and the cradles come at the finish (step 34).
Tip Two ceilings meet here: the 1/8 ply at 75 1/2 over the first 4 in of the wardrobe, and the 8020 frame at 76 1/4 behind it, the line the shower ceiling hangs from. Scribe the panel to the 8020 line.NeedsWaiting on 1 of 1Laundry cubby side panel, 1/2 ply scribed to the ceilingready to order
Floorsteps 27 to 28
- The vinyl is already out (step 6). With the base dry-laid and its drain over the mark, trace the base onto the subfloor.
- Cut the 5 in hole at the drain mark.
Caution Look underneath once more before the hole saw: the utility box is under the first 16 in from the driver wall and the chassis rail at about 25.NeedsWaiting on 2 of 2Click and Seal 2 in drain (with the base)ordered5 in hole saw and arborready to order- 2 in Schedule 40 up into the hole, cut flush with the subfloor (the curbed Fundo detail).
- Under the floor it drops into the 8 in channel behind the new driver front Buyers box, the HepvO runs aft in that channel, and a short 2 in leg goes into the box, where the grey valves are (grey-water.html). Falling the whole way.
- Leave the HepvO where you can reach it from below: it is the part that gets cleaned.
- Water test it before anything covers it.
Waterproofsteps 29 to 31
- Mix the thinset. Skim and comb both the subfloor and the base underside, then set the base: 3/16 to 5/16 compressed.
- Click and Seal drain into the 2 in pipe, per its manual.
- Both curbs in thinset on the bare subfloor. Joint Sealant at every base-to-curb joint.
- Now the D1 apron, kitchen side, 20 3/4 long, over the curb's kitchen face. Bond it to the curb's face with construction adhesive; a screw through each end into the wardrobe panel and the partition's edge, none into the curb.
Caution Follow the Fundo and Click and Seal manuals for bead sizes and cure times, not this page.NeedsWaiting on 7 of 7wedi Fundo Primo base, 36 x 72, center drain, US9100006orderedClick and Seal 2 in drain (with the base)orderedD1 curb, white oak core under 1/4 wedi, site-builtready to orderwedi PRO-SET modified thinset, 25 lbready to orderThinset trowels, mixing paddle, bucketready to orderwedi Joint Sealant, 10.5 ozorderedD1 apron, poplar 1x4, kitchen sideready to order- 1/4 in wedi everywhere (Jeff, 2026-10-13), bonded in modified thinset with a 1/4 square notch: first 6 mm okoume ply on the driver wall and the cable box face, glued and screwed to the framing; everywhere else the board goes straight on solid backing; wedi washers and screws at the seams. Cab wall: a hole through the board at each bolt head, the heads sealed flush.
- Cab wall, before each board goes up: dab paint on every bolt head it will cover, press the board into place, and take it down. Cut a hole right through the board at each mark, just bigger than the head: the tallest head is 1/4, the board's thickness, so it ends flush. These bolts hold the box to the cab, so keep them reachable: set a printed sleeve in each hole in Joint Sealant, and close it with a cap on an O-ring, flush with the microcement.
- Ceiling: cut the two light holes through the wedi and the skins at the leads, to the lights' cutout size; seal the cut edges.
- Wardrobe: the IKEA side is melamine, which thinset grips badly. Scuff it hard and bond with wedi 610 adhesive, then screw through into the panel; check the panel's thickness first so no screw comes out inside the wardrobe. Partition: bond to the plywood and screw.
- Ceiling: one board, kerfed on the back across the curve, half its thickness deep, 1/2 apart, after a test piece bends without crazing (the ceiling curve, below the steps). Ask wedi to confirm the spacing.
- Joint Sealant on every seam, every screw head, the curb joints and round the two mixer holes (pipe collars).
- Cut the wedi tight round the fan sleeve and seal it all the way round.
NeedsWaiting on 10 of 10wedi building panel 1/4 in, 48 x 60 (US8000013)ready to orderPly backing under the wedi, 6 mm okoume BS-1088, 4 x 8ready to orderModified thinset for the boards, 25 lb (ANSI A118.15)ready to order1/4 x 1/4 square-notch trowelready to order#8 x 3/4 stainless screws (cab wall, partition, wardrobe: nothing may come through)ready to orderwedi tabless washers, 100TBDCab bolt access: printed sleeve and O-ring cap for each box-to-cab boltTBDConstruction adhesive for the ply backing (PL Premium)ready to orderwedi fastener kit, 100 screws + washersorderedwedi Joint Sealant, 10.5 ozordered- Let everything cure. Plug the drain and fill the base to just under the curb tops.
- Leave it a day. Check underneath, in the cab and behind the wardrobe.
- Hose the walls. Fix anything now, before the finish hides it.
Caution No finish goes on until this passes.
Finishsteps 32 to 34
- CimentART's shower system over the wedi, nothing else mixed in: fiberglass mesh, Primer, two coats of Aqua Base, the Aqua microcement, one coat of sealer, two coats of two-part varnish.
- Keep the drain cover flush, the curb tops sloped into the shower, and leave clean, flat lands where the gaskets and stops will sit.
- Nothing bridges a door gap or a hinge.
Caution CimentART wants a rigid support with no movement, and no puddles anywhere. Ask them about a truck before you start, and check the floor drains dry first.Tip CimentART lists wedi as an accepted substrate. Do NOT put it straight over a sheet membrane like Kerdi: they want 1/2 to 1 cm of mortar between.NeedsWaiting on 2 of 2Stainless drain cover, US1000057orderedMicrocement: CimentART Aqua shower systemTBD- Mixer through its two holes into the blocks, supplies on with the included 1/2 in adapters, collars sealed.
- The hook above the shelf (into its pad, or a magnetic one), the hand shower on it. The Scandvik's rail is not used.
- Fan into its sleeve, wired to its QuinLED channel (500 mA fuse). Cowl outside on sealant, mouth down. The slots low in D1 let the air in.
- The two ceiling lights into their holes, gasket or sealant behind the flange, wired to two QuinLED channels: white and red.
NeedsWaiting on 6 of 6Shower lights: two recessed 12 V pucks, wet-rated (IP67), white and redready to orderVETUS FAN12 extract fan, 12 V, two speedorderedVETUS SCIROCCO cowl, 316 stainlessorderedFan control: off / low / high and a run-on timerTBDBlack fan cover, printed: floating disc and ringready to orderShower mixing valve (which one: not chosen)TBD- The flap: 30 5/8 wide, 3 3/16 tall, on a piano hinge along its bottom edge so it drops down. Cut a row of vent slots through it: dirty clothes shut in a box next to a shower go musty.
- Two push-button latches at the top corners, the kitchen's latch. Nothing in the truck opens on a bump.
- Print the two U-cradles and screw them to the wardrobe top at the front corners, just behind the closed flap.
- Sew the mesh liner with a sleeve along its front hem, slide the dowel in, and drop the dowel into the cradles. Stuff clothes in over the dowel.
- To empty: drop the flap, lift the dowel out of the cradles, pull the whole liner out by it.
Tip Roughly 1.2 cu ft: about 4 or 5 days of T-shirts, shorts, underwear and socks for two, loosely stuffed. Test with a real pile before sizing the liner.NeedsWaiting on 5 of 6Laundry hamper flap with vent slots, hinged at the bottom, 1/2 Baltic birchhave itMesh hamper liner, a tray that pulls outready to order1/2 in hardwood dowel, 36 inready to orderU-cradles for the liner dowelready to orderPiano hinge, 30 in, for the flapready to orderPush-button travel latches for the flapready to order
Doorssteps 35 to 38
- Measure the finished opening between the upright, the head and the curb, at three places each way.
- Cut the 12 mm Baltic birch to 18 wide and the measured height less the gaps (about 67 if nothing moved).
- Both faces: the microcement maker's plywood sequence with full mesh, so the kitchen face matches the frame round it. All four edges and every hole: sealed.
NeedsWaiting on 1 of 2D1 air slots, routed through the doorready to orderD1 leaf, 12 mm Baltic birchhave it- The hinge sits in the corner at a right angle: one 3/4 leaf on the upright's opening face, shower side; the other on the door's shower face at its hinge edge; the knuckle in the corner. A screw in every hole: #6 x 3/4 into the upright, #6 x 3/8 into the door.
- The gasket: EPDM bulb seal stuck to the back face of the notch, up the jamb and along the head. The closed door's lip squeezes it to about 1/8. From the kitchen you see only the dark 1/8 gap; from the shower, the lip.
- The magnets' steel strikes: screwed to the notch's back face, opposite the magnets in the lip.
- The sweep: a rubber blade along the bottom of the door's shower face, just touching the curb top.
- The mirror, once the kitchen face's microcement has cured and been sealed: 1/8 safety-backed glass, 14 x 56, polished edges, on mirror mastic (neutral cure, mirror-safe), 1 in from the hinge edge, its bottom 13 1/8 up. Tape it in place while it cures. Safety backing so a crack on a rough road stays in one piece.
- The latch at 38 in: its body on the door's shower face, its bar reaching over the lip into the keeper on the jamb's shower face; the handle on the kitchen face, its thumb lever through the door. Set the keeper so the latched door squeezes the gasket.
Tip Shut: the latch holds it, the magnets pull the corners in, the lip squeezes the gasket. Open: thumb the handle in the kitchen, or lift the bar in the shower.NeedsWaiting on 8 of 8D1 mirror, kitchen face: 1/8 safety-backed glass, frameless, polished edgesready to orderTACO Marine 304 stainless piano hinge, 1 1/2 x 72, 0.037 (H14-0112A72-1)orderedD1 latch, worked from both faces, and its keeperTBDD1 corner magnets: cup magnets and steel strikesready to orderD1 latch backing plateTBDHinge drilling jigTBDD1 open-stop bumperTBDDoor seals, EPDM bulb (D1 and D2)TBD- Measure head to curb, finished.
- 12 mm Baltic birch, the offcut of the D1 sheet, 20 11/16 wide (Jeff, 2026-10-12: no 3/4 okoume). The hangers screw into the top rail, not the panel, so 12 mm is plenty.
- Glue and screw the 5/4 hardwood top rail along the top edge, centred: it is about 7/8 thick, so it stands about 3/16 proud of each face. Round its edges. That gives the hangers 20 mm or more.
- Check the BG1 floor guide fits a 12 mm bottom edge before you cut (ask Woodward's with the track order).
- Seal every face and every edge the same way, then microcement both faces, like D1: a door with one wet face and one dry face cups unless both sides match. No wedi on the doors.
- After the microcement: the track bracket (a bent stainless angle, or Husky's own face-fixing bracket if Woodward's has one) is THROUGH-BOLTED above the hole (Jeff can reach the cab side): 1/4-20 stainless bolts about every 7 in, through the bracket and the finished wall with a stainless fender washer and a nylock on the cab side (cap nuts if you want them tidy), a dab of threadlocker on each. At each bolt, drill the wedi oversize and set a stainless or nylon sleeve the wedi-plus-microcement thickness, so the bracket clamps on the sleeves, not the foam; sealant round every sleeve. Cut the track where the mockup said (about 41 1/2) and screw it up into the bracket's flange.
- Hangers into the top rail, hang the leaf, set the clip stops, the BG1 guide on the infill by the doorway (never through the curb).
- Jamb seal and sweep. A latch that holds it closed and another that holds it parked: it must not slide on the road. Then the track cover.
NeedsWaiting on 8 of 8Door seals, EPDM bulb (D1 and D2)TBDHusky PC100/200 hangers, clip stops, BG1 guideready to orderHusky track, aluminium, 6 ft (cut to 41 1/2)ready to orderD2 track cover, bent aluminiumTBDD2 bracket bolts: 1/4-20 stainless, fender washers and nylocks on the cab side, sleeves through the wediready to orderD2 track bracket: a bent stainless angle the track hangs fromTBDD2 BG1 guide bracketTBDD2 travel latches, closed and parkedTBD
Commissionstep 39
- Full shower with both doors shut. Watch the curbs, the D2 sweep and the drain.
- Open and shut both doors twenty times. Then drive a washboard road and listen.
- Re-check the latches, the hinge screws and the track stops after the first week.
- Run the fan on its timer after the shower; hose the outside of the cowl and check nothing drips in.
Notes9
- Custom parts for the shower and both doors (pulls, track cover, track plate, stops, latches, jigs), designed as code for the printer and SendCutSend: Custom parts.
- Design authority: Shower construction (2026-08-24). This page is the order of work for that design. Room 52 1/4 x 21 1/4, measured; finished about 47 13/16 x 20.
- ASSUMED on this page, measure before relying on it: the 80/20 positions, where the passthrough cutout sits, the cab overlay thickness (3/8), the mixer height (40), the D2 head height, the microcement thickness (0.10).
- Microcement is CimentART, Aqua range (Jeff, 2026-09-30). Their application guide lists wedi as an accepted substrate and gives a full shower system that needs no extra membrane. It says never to apply microcement directly over sheet membranes (Kerdi and the like): those need 1/2 to 1 cm of mortar first, which is why this build stays on wedi rather than Schluter. It also wants a rigid support with no movement: ask CimentART about the truck.
- Husky gear is rated 200 lb for a door under 15 lb: heavier than it needs to be, but it is what the design drew. A lighter option if Woodward's says no: Slid'up 100 (5/8 in min door, sold as a two-door kit).
- Hinge: the page orders the 0.060 leaf Guden (TS07060406-72) over the 0.040 one the design named. The earlier door study set 0.060 as the minimum for a door that rides on a truck.
- Extract fan (Jeff, 2026-10-12): the job is smell from a bagged Trelino, heat and drying wet gear. Weighed: the Attwood Turbo 4000 blower (about 100+ CFM real, loud, needs a box, an elbow and a flap), the MaxxFan Dome Jeff has (strong, but a roof fan: on a wall the lid lets rain in) and the VETUS FAN12. Chose ONE VETUS: about 25 to 30 CFM real is an air change every 1 1/2 to 2 minutes, 4 to 5 times a house bathroom's, silent and on 0.15 A all day. Flush on the cab wall behind the Pelican box, no box. A second blocking ring sits beside it with no hole, in case a second fan is ever wanted. Air in: five thin slots routed low through D1. Sound cover: the Marshall speaker on the other side of the partition. The Trelino's own fan is skipped (it is for composting; the solids are bagged).
- Waste: no 2 in HepvO exists. The 2 to 1 1/2 reducer is the plan; RectorSeal SureSeal 2 in and Green Drain GD2 are 2 in drop-in alternatives, fit under the Click and Seal body unchecked.
- The kit includes Joint Sealant (about 8 or 9 tubes, per Portland Direct): count before buying more.